Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, NOVEMBER 24, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running control wiring for the heating hot water system.
  • The demo contractor removed the remaining metal studs and electrical conduit from the offices along Gravier Street. 
  • The mechanical contractor continued piping the 1st Floor air handling units and connecting heating hot water piping to the VAV boxes on the 2nd Floor.
  • They continued installing ductwork in the 2nd Floor auditorium

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued terminating electrical wires at the ATS on the 2nd Floor.
  • Crews completed the asphalt paving near the C tower.

CSRB EXHAUST UPGRADE:

  • The contractor began installing the temporary exhaust ductwork in the 1st and 2nd Floor mechanical rooms.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor finished removing the light fixtures from the transformer vault in the basement.

CEB COVERED WALKWAY

  • The contractor continued building formwork for the two staircases.
  • They installed reinforcing steel at the staircase adjacent to the Lapeyre Miltenberger building.

ELEVATED WALKWAY RESURFACING

  • The contractor applied primer and leveling filler on the Lions/LSU Clinics Building and CSRB bridges.   
  • They applied the base coat to the CSRB bridge.