Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 9, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION

  • The contractor installed studs for the 2nd floor auditorium along the MEB side of the building. 
  • They installed ductwork and VAVs for the 1st Floor, near the Mens restroom.     
  • Workers continued applied the 3rd coat of stucco for the stairwells along S. Roman Street. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed one door frame between the generator room and the switchgear room.
  • They continued placing CMU block wall between the fire pump room and the switchgear room. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed fire caulking around the sump pump piping in the freight elevator pit.
  • They installed pipe hanger for the diesel fuel line in Room 139.