ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for the electrical receptacles on the perimeter of the auditorium. 
  • The demo contractor continued removing the remaining metal studs and electrical conduit from the offices along Gravier Street. 
  • The mechanical contractor continued installing ductwork in the 2nd Floor auditorium. 
  • The contractor completed programming the heating hot water system.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor compacted soil and placed tack-coating in trenches in the main driveway.

CSRB EXHAUST PROJECT:

  • The contractor installed the temporary duct for phase 1 on the 1st Floor.

CEB COVERED WALKWAY:

  • The contractor continued erecting steel canopy supports for the walkway roof adjacent to the CEB.

DENTAL SCHOOL CAMPUS ROAD REPAIRS:

  • The contractor installed base course material for the new concrete driveway at Army Boulevard.
  • They began the demolition of the existing driveway at Navy Boulevard.