Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, DECEMBER 8, 2010

ALLIED HEALTH.NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for receptacles surrounding the auditoriums.  
  • The mechanical contractor continued installing and insulating ductwork in the 2nd Floor auditorium and along the Gravier Street on the 1st Floor.
  • They completed relocating the copper piping for the compressed air line.
  • Workers continued to correct the stucco punch list items on the 1st Floor.  
  • The contractor started installing the structural steel for the generator platform in the switchgear room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed two door frames for the utilities chase on the ground floor.

CEB COVERED WALKWAY:

  • The contractor began grading the site on the end closest to the District Energy Garage.
  • They continued welding the steel canopy supports for the walkway roof.

DENTAL SCHOOL CAMPUS ROAD REPAIRS:

  • The contractor installed steel reinforcement and expansion joints in the Army and Navy Boulevard driveways.