Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JANUARY 13, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to correct the stucco punch list.
  • Additional metal studs were installed for the birthing labs on the 2nd Floor.
  • Sheetrock was hung on the exterior of the auditorium along Perdido Street. 
  • The contractor patched the floor in Room 138. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor pulled six feeder cables from the transformer vault to the new switchgear located on the 2nd Floor of the new elevated structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the ceiling in the 1st Floor elevator lobby.
  • Workers continue correcting items on the stucco punch list.
  • Granite was installed on the exterior wall of the switchgear room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor is running conduit in the basement for the elevator pit.
  • Parts were removed from the pit of passenger elevator #7.
  • Crews continued removing brick pavers along the side of the generator.

CSRB EXHAUST UPGRADE:

  • The contractor prepared the new ductwork for installation on the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continues fabricating the 3 inch heating hot water riser for the penthouse. 
  • They set the drain pans for the AHUs above the gross anatomy and oral pathology labs.