ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor installed sheetrock around the auditorium on the 2nd Floor. 
  • Workers continued running conduit from the emergency generator to the ATS on the 2nd Floor and to relocate panel X1A (1st floor emergency panel).   
  • Work on the stucco punch list continues.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the interior wall in the new switch gear and generator rooms and in the A-tower laundry room.
  • They started framing the soffit underneath the entry way of the new building. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the anchor plates for the mezzanine deck in the 2nd Floor pump room.
  • The completed the metal deck for the bookstore desk.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued removing elevator parts from the pit for elevators 7 and 8.
  • Crews continued removing existing heating water pipes and installing the 10 inch supply heating hot water pipe in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing electrical conduit on the 7th Floor.
  • They installed the ceiling supports on the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued to fabricate and install the heating hot water lines for the AHU above Oral Pathology.
  • Workers began running chilled water lines for the AHU above the Gross Anatomy lab. 

DENTAL SCHOOL LIGHTING REPLACEMNT PROJECT;

  • The contractor replaced an additional 20 light fixtures on the 6th Floor of the Clinic Building.