ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running conduit for fixtures and receptacles on the 1st and 2nd Floors.
  • Crews continue to correct flaws in the stucco on 1st Floor walls.
  • Workers continue to hang the steel beams for the generator platform in the existing switchgear and generator rooms on the 1st Floor. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits in the basement to relocate existing electrical panels to the 1st Floor.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing electrical conduit on 7th Floor in the Perdido Street corridor. 

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued ductwork (non-asbestos) demolition on units 8B (Oral Pathology) and 8D (Gross Anatomy lab). 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 38 light fixtures on the 8th Floor (on both sides of the Clinic Building).  

ALLIED HEALTH/NURSING BLDG 2ND FL NETWORK CLOSET:

  • The contractor continued to remove floor tile from the space,
  • They hung the plywood backing for the IT rack.