ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed the plaster ceiling on the 2nd floor bridge area to make way for the structural steel. 
  • They installed ductwork on the 1st Floor near the security guard desk and continued insulating ductwork on the 2nd Floor.
  • Workers continued installing sheetrock near the birthing lab and the 2nd Floor network closet. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to caulk the exterior concrete panels that form the walls of the new elevated structure.
  • An electrical feeder was pulled for the MDP panel in C-Tower.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the back corridor of the 1st \Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • They excavated for the electrical duct bank near the generator.
  • Electrical conduit was installed for panel EFC on the 4th Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running the reheat lines to the VAV boxes above the Gross Anatomy lab.
  • They started running reheat lines to the VAV boxes above the Oral Pathology lab. 
  • Workers continued installing VAV boxes and supply ductwork for the AHU above Oral Pathology. 

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed 22 light fixtures on the 5th Floor.