ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor welded additional structural steel for the new walkway storefront.  
  • Workers continued to remove the wall paper from the 2nd Floor main corridors.
  • The contractor continued pulling data wires for the 1st Floor offices. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to pulling the feeder for the MDP-2 panel in the B-Tower.
  • Crews continued to run the water line for the fire pump.
  • They continued caulking the interior side of the precast concrete panels.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed ceiling grid in the back portion of the 1st Floor. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chill water piping in the basement.
  • They continued installing the underground storm drain line near the loading dock area.
  • Workers began installing underground electrical conduit for the duct bank toward Tulane Ave.

CEB COVERED WALKWAY:

  • The contractor poured concrete for the ADA ramp and installed the base layer of roofing felt for the main walkway roof.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor replaced the heating hot water riser on the 7th Floor.     

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed an additional 23 light fixtures on the 5th Floor.