ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor installed oval ductwork into the AHU on the 2nd Floor.
  • They ran heating hot water to VAVs and ran chill water lines for the 1st Floor units.   
  • Workers continued painting the 1st Floor office areas near Bolivar St.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • Wiring was pulled from the 1st Floor electrical closet to the new 3rd Floor electrical panel for the stoves in Tower C. The stoves in Tower C are now energized through new switchgear.  
  • The contractor began caulking the exterior wall of the new building.
  • The floor in the storage room in Tower A was sandblasted.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • Conduit was run in Room 211 for the 7th and 8th Floor AHUs.
  • The contractor attached the steel decking for the 1st section of the mezzanine platform. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • The freight elevator shaft wall in the basement was demolished.
  • The contractor installed an electrical junction box in the 3rd Floor mechanical room located on the back side of the building. 

CSRB EXHAUST UPGRADE:

  • The contractor installed electrical conduit in Room 139B.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued fabricating the heating hot water and chilled water risers. 
  • The new chilled water lines were painted. 

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • An additional 20 light fixtures were installed on the 7th Floor of the Clinic Building.