Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MARCH 17, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued finishing walls along the new 2nd Floor corridor on the MEB side of the building.    
  • Workers continued running three 4-inch emergency power conduit on the 2nd Floor.
  • Light fixtures were installed in Room 138.    
  • The contractor painted door frames and installed door hardware in the offices on the 1st Floor. 
  • They installed the framing for the sheetrock ceilings in the 1st floor bathrooms. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor finished relocating panels 1X and MDP-X to the 3rd Floor electrical room in B-Tower.
  • The existing transformer "D" was removed from behind the B-Tower electrical closet on the 1st Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water pipe in the 2nd Floor pump room and piping the building side of the heating water system to the pumps. 
  • Seven stainless steel doors on the 1st Floor were primed.
  • Lockers were installed in the Mens restroom.
  • The contractor installed the helium tank supports in the bookstore.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor installed sewer pipes connecting to the new sewer man hole near the electrical duct bank.
  • Additional underground electrical conduit was installed for the duct bank along the driveway.
  • The contractor continued installing 8-inch chilled water pipes in the basement.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing re-heat lines to the VAV boxes in the corridor near the Oral Pathology labs. 
    • They have completed 9 of 15 boxes and started running the home-runs to the heating hot water riser. 

  • Conduit was run from the control panels to the AHU units and control wire for thermostats on the 8th floor above the Oral Pathology unit was installed. 
  • Crews started insulating the supply ductwork in the penthouse for the unit above the Oral Pathology lab.  
  • The chill water tie-ins for the unit above Oral Pathology were finished. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor pressure-washed the exterior wall (3rd & 4th bay) on the north side of the Clinic Building and the (5th & 6th bay) south side of the Administration Building.

DENTAL CAMPUS ATHLETIC FIELDS:

  • The contractor continued final grading the softball outfield and the multi-purpose sports field.
  • They excavated for a new catch basin near the Moss Street entrance.
  • Workers continued installing the softball backstop.

DENTAL SCHOOL LIGHTING REPLACMENT:

  • The contractor replaced another 18 light fixtures on the 3rd Floor of the Clinic Building with high-efficiency fixtures. 

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor continued to install direct-buried electrical conduit between the new light pole bases.