Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, APRIL 5, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor drilled holes through the generator room walls to allow for stand-by power conduits. 
  • Crews continued welding structural steel below the walkway along the Gravier Street side of the building.   
  • Workers continued prepping the 1st Floor for the epoxy coating.  

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the 4 remaining doors (23 total) on the 1st Floor and 4 doors on the 2nd level of the new building.
  • They continued installing the frames for the louvered panels on the 2nd level of the new addition building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor completed removing the existing heating water piping.
  • The 1st of two clear coats were applied to the 1st Floor epoxy flooring.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued erecting concrete forms for freight elevator #4 and passenger elevator #8 in the basement.
  • They continued welding and installing 8-inch chilled water pipes in the basement.
  • The concrete forms were removed from the transformer vault walls.
  • The contractor began erecting scaffolding up to the loading dock canopy.

CEB COVERED WALKWAY

  • The contractor continued installing flashing and snap-on seam strips.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued pressure washing the east side of the Clinic Building.
  • They continued removing and installing caulking from the south wall of the Clinic Building and the east wall of the Administration Building. 

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor replaced the heating hot water riser in the stairwell near Oral Pathology. 
  • They ran conduit and control wire for the fire alarms in the penthouse.   
  • Crews continued removing ceiling grid around in hallways around Room 2110 (near the Dean’s office and Faculty Practice) in the Administration Bldg. 
  • They removed control and electrical conduits from the ductwork in Room 2110. 
  • The controls contractor also removed all pneumatic connections to the mixing boxes on the 2nd Floor near the Deans Office.

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 20 fixtures on the 2nd floor of the Administration Building with high-efficiency fixtures.