Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MAY 27, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • Restroom fixtures are being installed on the 1st Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor insulated the fire pump exhaust pipe on the 2nd level of the new building.
  • Workers swept and cleaned all the storage rooms on the ground floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the piping manifold for the domestic water pumps.
  • They continued installing the electrical conduit for the fire pump controller.
  • Crews continued installing the generator fuel line in the grounds keeping closet on the 1st Floor.
  • The contractor created floor penetrations on the 2nd Floor for the fire water piping.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits and junction boxes on the 3rd Floor.
  • Workers continued removing the elevator shaft in the library area.
  • An additional 14 piles were driven in the Lakeside lot. 74 of the 110 piles have been driven.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing riser #4 on the 7th Floor.

DENTAL SCHOOL CLINIC AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the supply duct and chill water lines for unit 8D. 
  • They continued to install the control wires for units 8A and 8D.
  • The contractor started up unit 8D.  All four units are running on the 8th Floor. 
  • The ceiling grid was installed in Central Sterilization and on the 8th Floor.