Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MAY 30, 2011

NOTE: Many of the contractors observed the Memorial Day Holiday.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the electrical conduit for the fire pump controller.
  • Workers continued installing the generator fuel line in the office area on the 1st Floor.

CSRB EXHAUST UPGRADE:

  • The contractor began installing temporary ductwork on the 2nd Floor.
  • Crews cut the roof penetration for exhaust system #1.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor installed the ceiling on the 8th Floor and continued removing the ceiling on the 3rd Floor.