Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JUNE 10, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wood wall panels on the 2nd Floor.
  • They continued installing the stud wall between the mechanical room and auditorium on the 2nd Floor.
  • Electrical conduits were installed in the 2nd Floor auditorium.      

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the containment pipe for the diesel fuel line on the 8th Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits on the 3rd Floor.
  • Crews continued demolishing the elevator shaft wall in the basement.
  • The contractor poured concrete for the areaway around the exterior of the Lakeside lot.
  • Workers began to install gypsum board along the window wall in 3rd Floor offices.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor installed control wires for VAV boxes on the 3rd Floor of the Clinic Building.
  • They installed chill water pipes for unit 3B on the 3rd Floor.