Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JUNE 16, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wall panels on the 2nd Floor,
  • They continued pre-fabricating the heating hot water lines for the bridge area.       

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line on the 1st Floor.
  • Starters for the domestic water pump on the 2nd Floor were installed.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 2nd Floor.
  • Crews continued demolishing the elevator shaft wall in the basement.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued to pressure test the newly installed heating water lines in the Clinic Building.
  • Workers continued running chilled and heating hot water lines to unit 3-B. 
  • The contractor continued installing supply ductwork for unit 3-B.   
  • The asbestos abatement of unit 3-A was completed. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued installing new caulk on the penthouse, west, and east sides of the Clinic Building and sealed the exterior panels on the north side of the Administration Building.