Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JULY 1, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  
  • Crews framed the temporary walls for the monumental stairwell project. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line casing in the electrical rooms on the 2nd and 3rd Floors.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the 8 inch chilled water line in the basement.
  • Workers continued installing conduits on the 3rd Floor.
  • Crews formed up 2 additional pile caps in the Lakeside lot. Seven of the twelve pile caps have been formed.
  • The contractor continued forming the freight elevator shaft wall in the basement.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 3A in the Clinic Building.
  • They continued to insulate the ductwork for unit 3B. 
  • AHU 6A was set in place.
  • The contractor set VAV boxes for unit 6A.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and on the penthouse of the Administration Building.