Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JULY 15, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing sheetrock on the rear wall of the auditorium.
  • Floor epoxy was applied to the ramp in the auditorium. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 2nd Floor.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing new ductwork on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
  • They continued installing supply ductwork for unit 3B and 6A. 
  • Crews continued insulating ductwork and heating hot water lines for unit 3A and 3B. 
  • The contractor installed ceiling tile for unit 3A.
  • Workers continued installing the controls for units L2A and L3A in the Administration Building.