Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JULY 25, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Crews continued installing metal stud bracing along the corridor wall on the 2nd Floor.
  • Workers continued installing steel re-bar in the pile cap forms.  Formwork completed: 12 of 12; rebar installed: 10 of 12; and concrete placed: 4 of 12.

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor began setting the fire pump on the 2nd Floor.
  • They are framing the ceiling in the 2nd Floor auditorium.
  • Crews started installing the second layer of gypsum board in the mechanical room behind the auditorium.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued to demolish the existing outside air duct for unit 3B in the Clinic Building. 
  • Workers continued installing heating hot water lines for units 6A and 3A and insulating chilled and heating water lines for unit 3A. 
  • The controls contractor continued installing control wiring for units 3A and 6A. 
  • The contractor continued framing the hard ceiling in the Mens restroom and installing the drop in ceiling on the 3rd Floor of the Clinic Building. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing old caulk and installing new caulk on the north side of the Power Plant.