Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 26, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is framing the ceiling in the corridor behind the auditorium.
  • They continued installing second layer of gypsum board in mechanical room behind the auditorium.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Workers continued installing 6 inch domestic water line in the basement.
  • Crews finished installing steel re-bar in the pile cap concrete forms.  Formwork completed: 12 of 12; rebar installed: 12 of 12; and concrete placed: 4 of 12.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor is installing fresh air duct and supply duct for unit 3B in the Clinic Building. 
  • The new ductwork for units 6A and 3A was successfully pressure tested. 
  • Workers continued insulating chilled and heating water lines for unit 3A. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing old caulk and installing new caulk on the south side of the Power Plant.