CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st and 2nd Floors.
  • Crews continued installing the steam supply line in the basement.
  • The contractor continued building forms and installing steel rebar for the grade beam by the auditorium side of the building.
  • Workers began waterproofing the elevator pits of elevators 7 and 8.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing electrical conduit on the 7th Floor for fan systems 9 and 10.
  • Crews continued installing the round exhaust ductwork for exhaust riser 10 from the 3rd Floor to the 7th Floor.
  • The ductwork for phase 2A passed the pressure test.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor finished removing AHU 5A in the Clinic Building.
  • Workers continued removing light fixtures and ceiling tiles in the Library.