CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Crews continued installing the car rails and the buffer supports for the front passenger elevators.
  • They continued welding the chilled water and heating water pipes in the basement.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork for exhaust system #9 in Room 342.
  • They continued installing the ceiling support framing in the 2nd Floor corridors.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued running the heating hot water lines to the VAV boxes for unit 5A in the Clinic Building.
  • They continued installing chilled water for unit 5A and the ceiling grid for unit 6A. 
  • The asbestos contractor removed all asbestos ductwork and piping for unit 2A in the Clinic Building.
  • The contractor continued installing ductwork in the Library.
  • They installed control wire to the VAVs for unit L3A in the Administration Building.