Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, SEPTEMBER 9, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the main lobby of the 1st Floor and continued installing the elevator car rails for the front passenger elevators.
  • They continued installing formwork for the second section of the flood wall around the parking garage.

 

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork on the 3rd Floor for Exhaust System #9.
  • Workers continued plastering the ceiling in the 2nd Floor corridors.
  • Work continued on the installation of the VFDs for exhaust system #10.
  • The contractor began insulating the duct risers for exhaust systems# 9 & 10.

 

DENTAL SCHOOL AHU REPLACEMENT PROJECT:    

  • The contractor continued installing heating hot water lines for the AHU 5A VAV boxes in the Clinic Building.
  • They continued installing VAVs and insulating ductwork for unit 2A in the Clinic Building.
  • The contractor poured the concrete pad that will support the new unit 2A.
  • Crews finished insulating the new ductwork in the Library.
  • The contractor continued installing electrical conduit for the new ceiling layout in the Library.
  • Workers continued running the heating hot water lines and control wires to the VAV boxes for unit L3A.