Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, OCTOBER 12, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding steel structure for the new building and roughing in for exterior light fixtures in the new loading dock area.

CSRB EXHAUST UPGRADE PROJECT

  • The contractor continued installing the VFDs on the roof for exhaust system #2.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued running the heating hot water lines and installing the supply ductwork and the VAVs for unit 5B in the Clinic Building. 
  • The old unit 7D was demolished. 
  • Workers taped and floated the new wall for Room 7312.
  • The asbestos contractor removed the old ductwork serving unit 7A.   
  • Crews continued removing lights and ceiling from the Library.
  • The contractor built the forms for the concrete pads for AHUs L4C and L4D.