Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, OCTOBER 26, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault.
  • They continued roughing in the exterior light fixtures and plumbing risers for the new building.
  • Workers continued welding the steel structure for the roof level of the new MEP building.
  • The contractor began installing the metal decking which will support the concrete flooring on the 2nd and 3rd Floors of the new MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the shaft walls around the exhaust riser for fan system #3 on the 4th Floor.
  • Crews began installing conduit for the control system wiring for fan system #9.
  • A wall in Room 722 was repaired.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 5B in the Clinic Building.
  • They completed the installation of the chilled water lines for unit 5B. 
  • Workers continued installing the supply ductwork and VAVs for units 7A and 6B.
  • The contractor continued installing ductwork and began insulating the new ductwork in the Library. 

DENTAL SCHOOL ADMIN BLDG 1ST FLOOR ABATEMENT:

  • The contactor continued removing the old ductwork from the 1st Floor.