Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, NOVEMBER 17, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor removed windows in the existing building where the back corridor to the MEP building will be built.
  • Workers continued installing conduit from the back corridor to the MEP building on the 3rd Floor.
  • They continued installing storm drain pipes on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing conduit for the controls wiring of fan system #4.

DS CLINIC AHU REPLACEMENT   

  • The contractor continued insulating ductwork, installing ductwork transitions, and installing chilled and heating hot water lines for unit 6B in the Clinic Building.  
  • They continued insulating the chilled and heating hot water lines for units 7A and 7D.
  • Crews continued removing lights and ceilings as work on unit 4A gets underway.
  • The contractor started removing ductwork and piping in the unit 4A mechanical room.
  • The demolition of units L2B and L3B in the Administration Building continues. 
  • The contractor continued installing the new light fixtures in the Library ceiling. 
  • Workers began insulating the new ductwork installed for units L4C and L4D.