TUESDAY, NOVEMBER 29, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor removed the plaster ceiling from the corridor on the 2nd Floor.
  • The control panel enclosure for fan system #1 was installed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing the heating hot water lines for unit 6B in the Clinic Building.  
  • Workers continued to install the Men’s restroom ceiling on the 7th Floor.  
  • The contractor continued installing ductwork and VAVs for unit 4A in the Clinic Building.
  • They started installing hangers for the heating hot water lines that will serve unit 4A.
  • The contractor continued installing the ductwork and VAVs for unit L2B in the Administration Building. 
  • Crews continued to insulate the heating hot water lines for unit L3B.
  • The mechanical room doors for units L4C and L4D were installed and the units were started up.