Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, NOVEMBER 7, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault.
  • They continued to install conduits in the 3rd Floor corridor leading to the MEP building.
  • Crews are installing metal decking on the 4th level of the MEP building.

CSRB EXHAUST

  • The contractor continued installing conduit for the controls of fan system #2.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor pressure tested the new ductwork for unit 6B in the Clinic Building.
  • Workers continued installing the heating hot water lines and outside air ductwork for unit 7D.
  • They began insulating the new ductwork for unit 7D.
  • The control wiring for the 2nd, 5th and 7th Floors is being run.
  • The stainless steel ductwork in Room 3345 was replaced.
  • Ceiling grid and 20 light fixtures were installed in 5th Floor offices. 
  • The contractor continued installing and insulating ductwork and installing heating hot water lines in the Library.
  • The VFD wiring for units L4C and L4D is being installed in the Administration Building.
  • Crews installed new supply ductwork for unit L4D. 

DENTAL SCHOOL ADMIN BLDG 1ST FLOOR ABATEMENT:

  • The contractor continued removing ductwork and insulation on the 1st Floor.