Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, DECEMBER 21, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd level of the MEP building,
  • Crews continued installing storm drain pipe on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the exhaust ductwork for phase 2B.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 2B in the Clinic Building.
  • The new ductwork for unit 2B is being insulated. 
  • The contractor continued to work on the controls for the units. 
  • Workers to remove the ceiling grid and lights for units 7B and 7C and started removing ceiling grid and lights for unit 4B.
  • The contractor continued insulating the chilled water and heating hot water lines for units L2B and L3B in the Administration Building.  

DENTAL SCHOOL FOOD COURT:

  • The contractor continued removing existing stone veneer from walls.
  • They started building the temporary entrance near the horseshoe.