MONDAY, DECEMBER 5, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.
  • Crews are now installing electrical conduit on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed the fan motor for fan EF-2C.

DENTAL SCHOOL AHU REPLACEMENT PROJECT

  • The contractor completed installing unit 4A in the Clinic Building.  
  • They continued installing heating hot water line and began to install the chilled water lines for unit 4A.
  • Workers began the installation of the ceiling in the Men’s restroom and elevator lobby on the 6th Floor of the Clinic Building.
  • The contractor continued insulating the heating hot water lines that serve unit 6B.
  • Crews continued installing the ceiling in the Men’s restroom and elevator lobby on the 7th Floor.
  • The contractor continued installing ductwork and VAVs for unit L2B in the Administration Building. 
  • They continued installing chilled water lines and control wire for units L2B and L3B. 
  • New ceiling light fixtures are being installed in the Library offices.